South Tulsa Roads | Tulsa City Council (2024)

Stay up to date on road work projects throughout South Tulsa!

• Project Update as of: October 13, 2023

• Project Scope: Five lane with bike lanes and sidewalks on both sides of road

• Start Date: July 6, 2021

• Projected Completion Date: October 2023

• Funding Details: Improve Our Tulsa ($13,893,780)

August 25, 2022 Video Update:

South Tulsa Roads | Tulsa City Council (2)

Project Update as of: May 22, 2024

Traffic Control:

  • Left turns allowed at intersections 81st Street & Yale and 91st Street & Yale.

  • One lane opened in each direction.

  • 04.04.24 Two-way traffic in new northbound lanes.

  • 07.16.24 Two-way Divided Traffic (one-lane in each direction, divided by median).

Construction Activities:

  • Regular meetings with contractor to work on advancing schedule delays.

  • Corrective Action (C.A.) Inspections:

    • C.A. #1 (89th to 87th) held 04.30.34. C.A. List #1 distributed and requested resolutions underway.​

    • C.A. #2 (87th to 84th) held 05.09.24. C.A. #2 List distributed and requested resolutions underway.

    • C.A. #3 (84th to 81st) held 05.21.24. C.A. #3 List distributed.

Phase 1: COMPLETE

​Phase 2: COMPLETE (Minus wall staining, which is weather-dependent)

Phase 3: COMPLETE

Phase 4: Underway on west side of Yale Ave. as of 10.10.23

  • Walls Complete

  • Roadway: Complete​

      • 87th St. (Entrance to Southern Pointe Addition):

        • Patterned Concrete:​

          • License Agreement signed by HOA. Processing.​

          • Entrance to open to traffic after concrete testing indicates design strength has been met.

          • Concrete placement began week of 7.29.24.

          • Reopening of entrance on 8.9.24.

  • Signage & Striping:

    • Signing: Complete​

    • Southbound Stripe: Complete

    • Northbound Stripe: Complete 8.7.24

  • Landscaping: To be constructed this phase.​

    • 05.16.24: Irrigation install began week of 05.20.24. Plantings to be installed as irrigation zones are completed. Estimated completion of Landscaping in Aug - 2024.

    • 8.7.24: Irrigation and landscaping Complete

      • Median Islands (from south to north): (Approx. 100% Complete)​

        • Island 'A': Complete​

        • Island 'B': Complete

        • Island 'C': Complete

        • Island 'D': Complete

      • West Curbline + NW Grove Planting: Complete

      • East Curbline + 87th St. Grove Planting: Complete

      • System Programming and Testing: Complete

    • FINAL INSPECTION: Held 08.01.24

    • PUNCHLIST: Issued 8.1.24. All major items complete 8.5.24. Minor items to be complete during week of 8.12.24

    • GRAND OPENING: Scheduled for 08.19.24

      • Location and Format: TBD

• Project Scope: Divided six lane with sidewalks on both sides of the road with fall protection walls

• Start Date: November 15, 2021

• Projected Completion Date: August 192024

• Funding Details: Improve Our Tulsa ($29,257,000)

View the widening construction schedule here

Watch the Town Hall to discuss all aspect of this project here

View the PDF document of the Town Hall presentation here

South Tulsa Roads | Tulsa City Council (3)

• Project Update as of: May 22, 2024

• Project Scope: Five lane with bike lanes and sidewalks on both sides of street

  • Funding Sources: Vision Tulsa, Water Enterprise, Stormwater Enterprise, Improve Our Tulsa, and completed street projects.

  • Consultant: Garver

  • Consultant Design Status: 95% of pre-mylars have been submitted for review.

  • R/W Status: Ongoing- 11 of 20 parcels have been closed. 0 in negotiations, 2 pending closing. 6 removed from project. 1 in condemnation.

  • Utility Status: September 2024 is the early clear target date for ONG and Windstream.

  • Contractor: N/A

  • Construction Cost Estimate: $13,330,253.75

  • Construction Start: Advertisem*nt for bids scheduled for June 2024. Funding options being reviewed.

  • Construction Completion: TBD

  • Traffic Control:

    • N/A

  • Construction Activities:

    • N/A

  • Project Update as of: August 22, 2023

  • Project Scope: Widened concrete intersection with sidewalks

  • Funding Sources: Improve Our Tulsa

  • Construction Cost Estimate: $12,000,000

  • Construction Start : Construction funding is anticipated FY27

  • Construction Completion: TBD

  • Traffic Control:

    • N/A

  • Construction Activity:

    • N/A

• Project Update as of: February 14, 2022

• Project Scope: Replacement of waterlines, rehab concrete pavement, ADA sidewalk modifications and traffic signal upgrades

• Funding Details: STP Federal Funds and Improve Our Tulsa ($1,747,000)

South Tulsa Roads | Tulsa City Council (4)

• Project Update as of: March 15, 2022

• Project Scope: Concrete patching

• Start Date: April 15, 2021

• Projected Completion Date: February 2022

• Funding Details: Improve Our Tulsa ($2,228,000)

South Tulsa Roads | Tulsa City Council (5)

• Project Update as of: August 22, 2022

• Project Details: Five lane with sidewalks on both sides of the road

• Start Date: August 19, 2019

• Projected Completion Date: July 2022

• Funding Details: Vision Tulsa ($7,430,588.70)

South Tulsa Roads | Tulsa City Council (6)

• Project Update as of: November 15, 2021
• Project Scope: Asphalt overlay

• Funding Details: Improve Our Tulsa ($1,414,641)

South Tulsa Roads | Tulsa City Council (7)

• Project Update as of: February 14, 2022

• Project Scope: Concrete patching

• Start Date: February 15, 2021

• Funding Details: STP Federal Funds and Improve Our Tulsa ($2,987,000)

South Tulsa Roads | Tulsa City Council (8)

• Project Update as of: December 7, 2021

• Project Scope: Improved intersection with turn bays, five lane with sidewalks on both sides of the road.

• Funding Details: Improve Our Tulsa ($8,752,795)

South Tulsa Roads | Tulsa City Council (9)
  • Project Update as of: June 4, 2024

  • Project Scope: Arterial street rehabilitation, stormwater improvements, sidewalks, and waterline replacement.

  • Funding Details: Improve Our Tulsa

  • Construction Cost Estimate: TBD

  • Construction Start: TBD

  • Construction Completion: TBD

  • Traffic Control:

    • N/A​

  • Construction Activities:

    • N/A​

Sometimes there are minor projects that are slated to take a week or even days to complete that we still want to keep you aware of.

1) Memorial Drive, 71st to 81st

• Project Updated as of: June 4, 2024

• Project Scope: Raise stormwater curb inlets and aprons on the outside lanes of Memorial Drive. Remove and replace pavement near the improved inlets.

• Funding Details: Improve Our Tulsa 2 and Public Works ($250,000)

Memorial Drive & US-169 Interchange

• Project Update as of: May 22, 2024

Read more about this project on ODT's website here.

Project Improvements:

○ Add Traffic Control Devices

○ Add capacity to roadway

○ Intersection Modification

Traffic Impacts:

○ Phased construction used to maintain existing traffic

○ Truck route detour

Traffic Control:

○ North and southbound Memorial Drive will maintain two lanes in each direction between 93rd St. and 97th St. throughout the majority of the project, except for a brief period when northbound traffic will be narrowed to one lane under the US-169 bridge. No ramp closures are expected for either U.S. 169 or the Creek Turnpike during construction.

Drivers are urged to give full attention to the road throughout construction and be aware of shifting lanes and new traffic configurations as work progresses.

• Project Scope: The project will improve the U.S. 169 and Creek Turnpike interchange, constructing eastern Oklahoma's first diverging diamond interchange.

• Start Date: February 6, 2023

• Projected Completion Date: Spring 2024

• Funding Details: ODOT ($13,733,920)

South Tulsa Roads | Tulsa City Council (10)

101st and Garnett

There will be work done in this area that is done by the County, State and Federal entities. Please contact ODOT for more information:

Randle White, P.E.

District 8 Engineer

rwhite@odot.org

918-838-9933

For information on ODOT projects that may impact your commute, you can find map/construction information here.

Learn more about Tulsa County projects here.

South Tulsa Roads | Tulsa City Council (2024)

References

Top Articles
Valerie Cody Leaked
Nnnud
Nullreferenceexception 7 Days To Die
Skyward Sinton
Room Background For Zepeto
Sportsman Warehouse Cda
Think Of As Similar Crossword
CA Kapil 🇦🇪 Talreja Dubai on LinkedIn: #businessethics #audit #pwc #evergrande #talrejaandtalreja #businesssetup…
Costco in Hawthorne (14501 Hindry Ave)
How to Watch Braves vs. Dodgers: TV Channel & Live Stream - September 15
Ohiohealth Esource Employee Login
Edible Arrangements Keller
4302024447
Connexus Outage Map
Hijab Hookup Trendy
Hartland Liquidation Oconomowoc
Shreveport Active 911
Cbs Trade Value Chart Fantasy Football
Guidewheel lands $9M Series A-1 for SaaS that boosts manufacturing and trims carbon emissions | TechCrunch
Grandview Outlet Westwood Ky
Carson Municipal Code
Band Of Loyalty 5E
Purdue 247 Football
Form F-1 - Registration statement for certain foreign private issuers
Deshuesadero El Pulpo
Restaurants In Shelby Montana
Table To Formula Calculator
Encore Atlanta Cheer Competition
Restored Republic
Tokioof
Spy School Secrets - Canada's History
The Venus Flytrap: A Complete Care Guide
2487872771
Song That Goes Yeah Yeah Yeah Yeah Sounds Like Mgmt
Tamil Play.com
Supermarkt Amsterdam - Openingstijden, Folder met alle Aanbiedingen
Closest 24 Hour Walmart
Aveda Caramel Toner Formula
That1Iggirl Mega
Babbychula
How to play Yahoo Fantasy Football | Yahoo Help - SLN24152
All-New Webkinz FAQ | WKN: Webkinz Newz
Mathews Vertix Mod Chart
Paul Shelesh
John M. Oakey & Son Funeral Home And Crematory Obituaries
CrossFit 101
Air Sculpt Houston
Jigidi Free Jigsaw
Union Supply Direct Wisconsin
Estes4Me Payroll
Southwind Village, Southend Village, Southwood Village, Supervision Of Alcohol Sales In Church And Village Halls
Ok-Selection9999
Latest Posts
Article information

Author: Mrs. Angelic Larkin

Last Updated:

Views: 5970

Rating: 4.7 / 5 (67 voted)

Reviews: 90% of readers found this page helpful

Author information

Name: Mrs. Angelic Larkin

Birthday: 1992-06-28

Address: Apt. 413 8275 Mueller Overpass, South Magnolia, IA 99527-6023

Phone: +6824704719725

Job: District Real-Estate Facilitator

Hobby: Letterboxing, Vacation, Poi, Homebrewing, Mountain biking, Slacklining, Cabaret

Introduction: My name is Mrs. Angelic Larkin, I am a cute, charming, funny, determined, inexpensive, joyous, cheerful person who loves writing and wants to share my knowledge and understanding with you.